Sample of Delays Report by Opteam
Notice of Delays Report · Temporary Construction Facilities in GOP · Sample · Opteam.ai
Notice of Delays Report

Executive Summary

Schedule Compliance Overview · Key Performance Indicators
Total Delayed Activities
231
1.2% of 19,205 total activities
Critical Path Delays
12
Require immediate intervention
Start Delays
7
3.0%
Activities not yet started past baseline
Finish Delays
224
97.0%
Activities in progress past baseline finish
⚠ Key Insight

Finish delays dominate at 97% of all delayed activities, indicating execution bottlenecks rather than late starts. Of these, 12 critical path activities require immediate intervention to prevent further schedule erosion.

Notice of Delays Report

Delay Distribution Analysis

Breakdown by Type, Criticality, WBS, and Location
Delay Type Distribution
Start Delays
7(3.0%)
Finish Delays
224(97.0%)
Criticality Breakdown
Critical
12(5.2%)
Non-Critical
219(94.8%)
By WBS Category
Construction
201(87.0%)
Engineering
22(9.5%)
Procurement
8(3.5%)
By Tower / Location
Tower A
101(50.6%)
Tower D
88(44.2%)
Podium Specific
10(5.0%)
By Trade / Discipline
Electrical & ELV
58(28.1%)
Plumbing & Sanitary
41(17.7%)
Mechanical / HVAC
40(17.3%)
Fire Fighting System
33(14.3%)
Paint
8(3.6%)
Plaster
7(3.0%)
Block Works
5(1.3%)
Access & Clearances
3(1.3%)
Miscellaneous Finishing Works
2(0.9%)
By Floor Level
Level 1
17(11.7%)
Level 3
26(11.3%)
Basement 1
24(10.4%)
Level 5
20(8.7%)
Level 4
20(8.7%)
Level 7
19(8.2%)
Level 6
17(7.4%)
Level 8
14(6.1%)
Level 2
13(5.6%)
Level 9
6(2.6%)
Level 10
5(2.2%)
Level 11 – Amenity Level
1(0.4%)
Notice of Delays Report

Key Findings & Observations

Summary of Critical Schedule Compliance Issues

Key Findings

~
224 finish-delayed activities remain In Progress and overdue, with none completed on schedule.
10 activities exhibit negative total float, the most critical being LV Switchgears at −89 days.
MEP trades represent 62% of all finish delays, driven by Electrical & ELV (58), Plumbing (41), and Mechanical/HVAC (40).
84% of finish delays are concentrated in Tower A (101) and Tower D (88), indicating localised execution bottlenecks.
7 activities remain Not Started, representing a risk of cascading schedule erosion.
Notice of Delays Report

Critical Delays

Most Severe Schedule Deviations by Total Float

Critical Start Delays

Top 3 by severity
Activity IDActivity NameBL StartBL FinishTotal FloatStatus
3G-PSM-MEP-LEA-1610 Delivery Lead Time (CD) – LV Switchgears (DB/SMDB/MCC/ESMDB/MMDB/Cap.Bank) 26-Nov-2025 04-Apr-2026 -89 Not Started
4G-GEN-FCD-ALM-1075 Start of Cast-In Channel installations at Level 12 05-Aug-2025 -69 Not Started
2G-MCP-STR-SUB-3210 Preparation & Submission of Shop Dwgs – Fog Forest Roof / Roof Crown 06-Mar-2026 11-May-2026 -18 Not Started

Critical Finish Delays

Top 9 by severity
Activity IDActivity NameBL StartBL FinishActual StartTotal FloatStatus
4A-P09-MEP-PLM-1025PLUM 2nd Fix (H/L Instl’n): Horizontal Drainage Pipes & Fittings03-Oct-202523-Oct-202501-Oct-2025-23In Progress
4A-GFL-MEP-ELE-1650ELEC 2nd Fix: Wiring & Cabling for ELV / Low Current Systems / ONU Dressing27-May-202512-Jun-202527-May-2025-14In Progress
4A-GFL-MEP-ELE-1640ELEC 2nd Fix: H/L Instl’n: Cable Trays / Trunking / Flexible Conduits / Cabling / Wiring / DB Dressing15-Apr-202505-May-202515-Apr-2025-14In Progress
4A-GFL-MEP-PLM-1230PLUM 2nd Fix (H/L Instl’n): Water Supply Pipes / Valves / Leak Test21-Apr-202510-May-202520-Apr-2025-9In Progress
2G-MCP-ARC-SUB-6000Preparation & Submission of Reflected Ceiling Plan (RCP) Shop Dwgs – B1-GF31-Oct-202520-Nov-202509-Sep-2025-4In Progress
4D-GFL-MEP-PLM-1230PLUM 2nd Fix (H/L Instl’n): Water Supply Pipes / Valves / Leak Test18-Jun-202509-Jul-202518-Jun-2025-3In Progress
2G-PSM-MEP-APR-8310Update till Approval of MEP Coordination Dwgs – B1-GF23-Jul-202508-Aug-202501-May-20250In Progress
4D-GFL-MEP-ELE-1640ELEC 2nd Fix: H/L Instl’n: Cable Trays / Trunking / Flexible Conduits / Cabling / Wiring / DB Dressing02-May-202522-May-202502-May-20253In Progress
4D-P09-MEP-ELE-1000ELEC 1st Fix: Install Conduits / Pullwires / DB & ONU Enclosures / Floor Boxes + H/L Hangers & Supports11-Oct-202524-Oct-202501-Oct-20258In Progress
Notice of Delays Report

Detailed Delay Activities

Complete Listing of All Delayed Activities

Start Delay Activities

Activities delayed on start based on the Excel source data
↑↓ Click any column header to sort
Activity IDActivity NameBL StartBL FinishTotal FloatLongest PathCriticalStatusWBS
4G-GEN-FCD-ALM-1075Start of Cast-In Channel installations at Level 1205-Aug-2025N/A-69NoYesNot StartedConstruction
3G-PSM-MEP-LEA-1610Delivery Lead Time (CD) – LV Switchgears (DB/SMDB/MCC/ESMDB/MMDB/Cap.Bank)26-Nov-202504-Apr-2026-89NoYesNot StartedProcurement
2G-MCP-STR-SUB-3210Preparation & Submission of Shop Dwgs – Fog Forest Roof / Roof Crown06-Mar-202611-May-2026-18NoYesNot StartedEngineering
4G-GEN-FCD-ALM-1080Cast-In Channels for Curtain Wall System05-Aug-202530-Jun-2027-79NoNoNot StartedConstruction
3G-MCP-ANT-MSA-1620Material Approval – Structural Steel to Fog Forest / Roof Crown06-Mar-202610-Apr-2026156NoNoNot StartedProcurement
3G-PSM-MEP-ORD-1740Order Placing – Chilled Water Pumps12-Mar-202616-Apr-2026165NoNoNot StartedProcurement
3G-PSM-MEP-LEA-1650Delivery Lead Time (CD) – Standby Generator Set26-Feb-202625-Jul-2026242NoNoNot StartedProcurement
Notice of Delays Report

Finish Delay Activities

Activities delayed on finish based on the Excel source data · 224 total · top 10 shown in this sample
↑↓ Click any column header to sort
Activity IDActivity NameBL StartBL FinishActual StartTotal FloatStatusTradeLevelTower
4D-P01-MEP-ELE-1560ELEC 1st Fix: Install Conduits / Pullwires / DB & ONU Enclosures / Floor Boxes + H/L Hangers & Supports17-Jun-202501-Jul-202517-Jun-2025205In ProgressElectrical & ELVLevel 1Tower D
4A-B01-MEP-ELE-1710ELEC 2nd Fix: H/L Instl’n: Cable Trays / Trunking / Flexible Conduits / Cabling / Wiring / DB Dressing10-Apr-202530-Apr-202510-Apr-2025206In ProgressElectrical & ELVBasement 1Tower A
4A-P01-GEN-PNT-1230Initial Painting to Plastered Walls (Primer / Stucco / 1st Coat)19-Jun-202510-Jul-202519-Jun-2025209In ProgressPaintLevel 1Tower A
4A-B01-GEN-PNT-1270Initial Painting to Plastered Walls (Primer / Stucco / 1st Coat)11-Jun-202502-Jul-202511-Jun-2025209In ProgressPaintBasement 1Tower A
4P-P01-MEP-ELE-1800ELEC 1st Fix: Install Conduits / Pullwires / DB & ONU Enclosures / Floor Boxes + H/L Hangers & Supports12-Dec-202522-Dec-202517-Sep-2025212In ProgressElectrical & ELVLevel 1Podium Specific
4D-B01-MEP-ELE-1710ELEC 2nd Fix: H/L Instl’n: Cable Trays / Trunking / Flexible Conduits / Cabling / Wiring / DB Dressing28-Apr-202517-May-202528-Apr-2025212In ProgressElectrical & ELVBasement 1Tower D
4D-P03-MEP-PLM-1160PLUM 1st Fix: Install Embedded Pipes to Walls09-Aug-202522-Aug-202522-May-2025215In ProgressPlumbing & SanitaryLevel 3Tower D
4D-P03-MEP-ELE-1420ELEC 1st Fix: Install Conduits / Pullwires / DB & ONU Enclosures / Floor Boxes + H/L Hangers & Supports24-Jun-202508-Jul-202524-Jun-2025215In ProgressElectrical & ELVLevel 3Tower D
4A-MEP-ELE-?ELEC 2nd Fix: H/L Instl’n: Cable Trays / Trunking25-Apr-202515-May-202525-Apr-2025215In ProgressElectrical & ELVLevel 1Tower A
4D-P01-GEN-PLT-1130Wall Plastering25-Jun-202509-Jul-202525-Jun-2025203In ProgressPlasterLevel 3Tower D
// 214 additional finish-delayed activities omitted from this preview. Full register available in the connected Opteam workspace.