Opteam

DELAY COST / FINANCIAL EXPOSURE

What is your delay actually costing?

Four inputs, contract value, days behind plan, critical-path activities slipping, and EOT exposure, combine into a range estimate of what a delay is costing right now. Output splits across the four cost streams a controls team defends in any claim: prolongation, disruption, liquidated damages, and acceleration.

Appears in the title of your downloadable PDF report.
01Project details
$75M
range: $1M · $2B · log scale
21d
range: 0 days · 180 days behind baseline
3
zero-float activities behind schedule · each adds ~4% load
extension-of-time claim strength · raises or lowers the recovery multiplier
02Breakdown
Prolongation
$-
Extended overhead, site costs, supervision.
Disruption & productivity
$-
Labour productivity loss and trade re-sequencing, typically ~35% of prolongation cost.
Liquidated damages exposure
$-
Liquidated damages, applied at 0.5–1.5% of contract value per week of delay.
Acceleration
$-
Overtime, additional shifts, and extra resources to recover the critical path, 20–50% of prolongation.
Total delay exposure
$-
cumulative across all four streams
Per week of delay
$-
marginal cost of each additional week
Opteam advantage

Detects this 3–6 weeks earlier than your reporting cycle.

  • Flags critical-path deviation before it compounds into a recoverable claim
  • Generates EOT narrative automatically from your live schedule data
  • Gives leadership the time to act, not react

Calibrated against AACE International cost engineering standards and HKA CRUX 2023 global claims data. Output is a range, not an estimate, your real exposure depends on contract terms and current critical-path posture.

Result Link copied
From estimate to evidence

Run this on your actual schedule.

You’re already on trial. Upload your P6 schedule file and Opteam will run this delay-cost analysis on your real project, with the same breakdown refreshed every progress update.

Opteam.ai
"+'
'+'
'+'
'+company+"Delay Cost report
"+dateStr+"
"+"
"+'
DELAY COST / FINANCIAL EXPOSURE
'+'

What is your delay actually costing?

'+'

Four inputs combine into a range estimate split across prolongation, disruption, liquidated damages, and acceleration.

'+'
Contract value: '+cv+"
Days behind: "+dw+"
"+'
'+'
Prolongation
'+ck1+'
'+ck1Desc+"
"+'
Disruption & productivity
'+ck2+'
Labour productivity loss and trade re-sequencing.
'+'
Liquidated damages exposure
'+ck3+'
Applied at 0.5–1.5% of contract value per week.
'+'
Acceleration
'+ck4+'
Overtime and extra resources to recover the critical path.
'+"
"+'
'+'
Total delay exposure
'+total+'
cumulative across all four streams
'+'
Per week of delay
'+perWeek+'
marginal cost of each additional week
'+"
"+'

Calibrated against AACE International cost engineering standards and HKA CRUX 2023 global claims data. Output is a range estimate.

'+''+"";var pdfWin=window.open("","_blank");pdfWin.document.write(html);pdfWin.document.close()})}})()}if(document.readyState==="loading"){document.addEventListener("DOMContentLoaded",_opteamInit)}else{_opteamInit()}})();